2020年12月30日,隨著雙護盾TBM碾碎最后一層巖石,青島地鐵1號線青島站-中山路站全區段順利貫通,標志著青島地鐵1號線左線全線貫通。
地鐵(tie)(tie)1號線青(qing)島(dao)站(zhan)-中(zhong)山路站(zhan)區段線路長(chang)約5.83km,是(shi)目前國內(nei)城(cheng)市地鐵(tie)(tie)單(dan)臺TBM施工最長(chang)的(de)區段,采用國內(nei)首創(chuang)的(de)連續(xu)皮(pi)帶機(ji)綜合快速出渣(zha)系統(tong),填補(bu)了城(cheng)市地鐵(tie)(tie)狹(xia)小場地TBM利用連續(xu)皮(pi)帶機(ji)出渣(zha)的(de)國內(nei)空(kong)白,建設過程中(zhong)更是(shi)創(chuang)造了最高日進(jin)尺28m,最高月(yue)進(jin)尺473m的(de)驕人(ren)成(cheng)績。
該區間(jian)施工過程中遇到諸多(duo)困難(nan):一是(shi)場地狹小,海泊(bo)橋始(shi)發站要(yao)供4臺TBM同(tong)時施工,為(wei)解(jie)決這一難(nan)題,經多(duo)方研究(jiu),通(tong)過垂直(zhi)皮帶(dai)機和垂直(zhi)儲帶(dai)倉(cang)的技術創新得以完(wan)美解(jie)決。二是(shi)工況(kuang)復雜,區間(jian)施工下(xia)/側穿老舊房(fang)屋105處、文(wen)保(bao)建筑物3處、軍事(shi)管轄區3處、人防15座、河(he)流1處;穿越不(bu)良地質段46處,多(duo)處富水,其(qi)中最(zui)長段120m;線路曲(qu)線段25處,最(zui)小轉彎半徑350m,過站10次、始(shi)發接收20次。這種種困難(nan)都使得改區間(jian)成為(wei)“最(zui)難(nan)區間(jian)”。
該(gai)項(xiang)目(mu)由1號線二標(biao)02工(gong)區(qu)中鐵十八局承建(jian),在項(xiang)目(mu)管理方(fang)(fang)面,通過全(quan)(quan)(quan)面推進“5831”示范班組標(biao)準(zhun)化建(jian)設活動(dong),重點方(fang)(fang)案和制度(du)先行(xing),同時(shi)采用視頻培訓、現(xian)場(chang)授(shou)課(ke)、班組長講堂、嚴格落實(shi)《軌行(xing)區(qu)管理九條規定》、崗(gang)位技能比武、月度(du)風(feng)險預控(kong)會(hui)、應急演(yan)練等(deng)(deng)豐富多(duo)彩的(de)活動(dong)降(jiang)低安(an)全(quan)(quan)(quan)風(feng)險,安(an)全(quan)(quan)(quan)按(an)時(shi)完(wan)成施工(gong)任務。在施工(gong)期(qi)間(jian),該(gai)項(xiang)目(mu)部(bu)不斷進行(xing)技術創新,取(qu)得15項(xiang)實(shi)用新型專利、發明專利3項(xiang)、科學(xue)進步(bu)二等(deng)(deng)獎1項(xiang),以(yi)及山東省(sheng)安(an)全(quan)(quan)(quan)文(wen)明工(gong)地等(deng)(deng)數項(xiang)省(sheng)部(bu)級(ji)榮譽。
2020年,在(zai)全(quan)(quan)力以(yi)赴(fu)確保北(bei)(bei)段(duan)(duan)(duan)通(tong)(tong)(tong)車的同時,青島地鐵(tie)一號線(xian)(xian)公司從未(wei)放松南(nan)(nan)段(duan)(duan)(duan)建設進度,在(zai)北(bei)(bei)段(duan)(duan)(duan)開通(tong)(tong)(tong)前(qian)夕已經完(wan)成工籌部署(shu)、人(ren)員調配(pei)增加、施(shi)工組織(zhi)、安(an)全(quan)(quan)管理、物資保障等各項措施(shi)。此次1號線(xian)(xian)左線(xian)(xian)全(quan)(quan)面貫(guan)通(tong)(tong)(tong),正是(shi)(shi)加快推進南(nan)(nan)段(duan)(duan)(duan)建設的鮮(xian)明成效(xiao)。北(bei)(bei)段(duan)(duan)(duan)通(tong)(tong)(tong)車前(qian)夕,1號線(xian)(xian)已經全(quan)(quan)面轉戰(zhan)南(nan)(nan)段(duan)(duan)(duan),按照(zhao)習總書(shu)記(ji)的話,起跑就是(shi)(shi)沖(chong)刺,我(wo)們有決心攻堅克難,有毅力披荊斬棘,早日實現1號線(xian)(xian)全(quan)(quan)線(xian)(xian)通(tong)(tong)(tong)車,為“十四(si)五”獻禮!
- 青島市地鐵規劃設計院有限公司 2021年第二次社會招聘公告 2022-05-24
- 青島市地鐵規劃設計院有限公司 2021年第一次社會招聘公告 2022-02-25
- 戰“疫”復工在行動益群公司進一步完善地鐵大廈疫情防控措施 2021-03-09
- 青島地鐵集團成功舉辦 2號線車輛基地高壓觸電事故應急演練 2017-01-27
- 青島地鐵工程建設安全質量隱患排查系統正式上線試運行 2017-01-27